Galldris Construction

Latest Posts:

Sorry, no posts matched your criteria.

Follow Us:

Back To Top
Galldris Finsbury Park Station

Finsbury Park

The Challenge

A 2 year program of deep shaft excavation that allowed construction of 2 new lift shafts, staircases and 2 cross platform underground passageways, leading to the new entrance of Finsbury Park.

The key challenges were posed by the location of Finsbury Park in the midst of a densely built and populated area. Works were carried out 24/7. It was a complex project where risk, logistics, noise pollution, vibration and waste management were all significant considerations.

Our project planning team identified significant efficiencies at every stage. Following the success of the first three stations, it was agreed that the Galldris and client teams should be retained to maintain continuity and knowledge in delivering all of the remaining stations

Client

Spencer

Galldris Value

£9m

Services

  • Basements
  • Rail
  • RC Frames
  • Tunnelling

Duration

2 Years

INNOVATION.

Finsbury Park was a complex project where Galldris were heavily involved with the Temporary works design in order to ensure the ground displacements were kept within tolerable limits.

The construction of ‘Squareworks tunnels’ using hand mining techniques were required to form the full excavation profile of the tunnel at Finsbury Park.

Once the full excavation profile of the tunnel or shaft was established in temporary works, rectangular steel frames were installed to resist the permanent loading conditions.

The steel frames were encased in mass concrete to meet the durability requirements of the frames.

Image Galleries.

Finsbury Park

The Galldris Difference

Exacavation was carried out between two live train railways. Steel frame temporary works were installed every metre. Shaft 1 was 20m x 7m by 7m deep. A linking cross tunnell off Shaft 1 was 10m x 7m to Shaft 2. Shaft 2 was an exacavated platform shaft of 7m x 7m by 14m deep. ‘Squareworks’ tunnelling excavation systems were used throughout. A combination of light exvacator and hand mining techniques were used. The larger of the two shafts, Shaft 1 was encased in concrete on completion. Before the installation of steel frames, which were later also encased in concrete.
6

Client:

Spencer

Galldris Value:

£9m

Location:

Finsbury Park

Duration:

2 years

Category:
Date: